Highway director details multiple bridge repairs; CivilCon outlines 20-month timeline for complex county-line bridge
Summary
Highway Director Clint Maddox updated commissioners on bridge inspections and repairs (Bridge 152, 107 culvert replacement), recommended tractor purchases, and heard a CivilCon presentation that estimated up to ~645 days for complex Bridge 145 work; commissioners accepted on-call engineering agreement pending legal review.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Putnam County Highway Director Clint Maddox updated the board on a slate of bridge and equipment matters, noting that work on Bridge 152 would begin the week of Feb. 16 and should be complete prior to the July 25 Dust Bowl race, while Bridge 211 may require replacement and could force a race detour. Maddox also said Bridge 107 would be replaced with a culvert and that multiple bridges are under review for concrete repair and pricing.
Maddox presented tractor bids and recommended two Bane-Welker units (a 2024 Case IH 140A priced at $122,451 and a 2025 Case IH L115 MSL priced at $173,350). Commissioner Rick Woodall moved to accept a pending on-call engineering agreement with Kurdziel Barker Engineering, Inc., subject to review by County Attorney Jim Ensley; the motion passed unanimously.
Representatives Duncan and Miller of CivilCon described a complex, historic, county-line bridge (Bridge 145) and provided a projected permitting and construction timeline estimated at roughly 645 days (about 20 months) under the firm's best-case assumptions. Commissioners asked for additional detail and review before selecting a design approach or contractor.