Summary

After opening quotes and bids, the commissioners accepted C&R Construction's low quote of $157,874.40 for Bridges 107 and 240 and approved Blankenberger Brothers' low bid of $409,367.36 for Bridge 78; motions for both awards were carried unanimously.

County Engineer Levi Leffert reviewed received quotes and bids and recommended contracts to the commissioners on March 2.

For Bridges 107 and 240 (deck overlay work), Leffert recommended accepting the low quote from C&R Construction at $157,874.40. For Bridge 78 (CR 600 W over the Patoka River), Blankenberger Brothers, Inc. submitted the low bid at $409,367.36 and Leffert recommended awarding that contract. Motions to accept both recommendations were duly seconded and carried unanimously.

Leffert also noted that deck overlay work for Bridges 107 and 240 is expected to begin in spring 2026; the plan is to close both bridges concurrently with anticipated closures of about 30–35 days each. The bid opening earlier in the meeting recorded several other bidders and quotes, which were taken under advisement prior to award.

The commissioners did not identify individual movers or seconders in the minutes; the record states the motions were carried unanimously. County staff will coordinate schedules and contractor notices as projects proceed.