Plevna lagoon ARPA project slowed by contractor contact problems; county told invoices must be in by Dec. 31

Fallon County Commission
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County and regional staff said contractor communication problems delayed a Plevna ARPA lagoon project but the vendor’s CEO has taken over; DNRC said invoices must be submitted by Dec. 31 for the grant to remain eligible even if construction happens afterward.

A regional development official updated the commission on ARPA‑funded work in Plevna intended to finish a lagoon project. The speaker said repeated communication problems with the prime contractor delayed construction through the fall, prompting the county and town to escalate contact to the contractor’s supervisor and now to the CEO, who has assumed responsibility and pushed the project forward.

“There’s no extensions, but they said as long as the invoices for construction are turned in by December 31, the work can happen even after December 31,” the speaker reported, summarizing DNRC guidance about invoice deadlines tied to ARPA administration.

Staff cautioned that 2022 bid prices may not cover current costs if construction happens later, and they have begun checking contractor availability and preparing reporting to meet DNRC invoicing requirements. The county is pursuing a PER (preliminary engineering report) and additional grants—such as Montana Main Street—to support sewer repairs and potential pipe replacement or lining.

Commissioners heard that the county will continue to press the vendor for timely submittals, that invoices must be returned in time to consume grant funds, and that close coordination with DNRC and local clerks is necessary to close the grant and unlock additional projects.