Fallon County reviews lagoon restart plan and road projects as crews prepare for spring work
Summary
County staff outlined a plan for restarting a lagoon pump system—ordering sterile bottles, coordinating hourly sampling during startup, and potentially using a chlorine 'start high' approach—while road crews briefed commissioners on maps, bridge inspections, 6th Street bidding and equipment maintenance.
Get email alerts on the Wastewater And Roads topic
No spam. Unsubscribe anytime.
County staff used the work session to walk commissioners through operational steps needed to restart a lagoon pump system and to update the board on road projects and field operations.
On the wastewater issue, staff said the county must coordinate sampling and testing before any restart. They recommended ordering sterilized sample bottles and scheduling sample collection so the first usable sample arrives roughly 90 minutes after startup; staff noted typical lab turnaround and the need to compare local and state lab results. "We have to make sure we're running... and when we turn it on, we start pulling samples every hour or two," the road/wastewater presenter said, explaining a plan to pump to the pond, draw it down and use that volume for initial tests.
Commissioners and staff discussed whether to rechlorinate or dose high at startup and then back off if tests show acceptable residuals; one staff member recommended starting at a higher chlorine level and reducing once passing results are confirmed. Staff also expressed concern about sample transit time to the lab and suggested delivering samples in person if needed to ensure rapid analysis.
Separately, the road mapping lead presented a GIS and field‑app plan that would let road crews upload photos, document culverts and signage, and tie bridge inspection ratings into the county map. Staff gave a timeline for the 6th Street Box project — a tentative October 30 completion if bidding proceeds on schedule — and said the DQ permit for the project is under review. Equipment maintenance notes included preparing trucks and cemetery rigs for spring service and diagnosing a broken hood and a faulty tire sensor on Truck 162.
Staff said they will finalize sterile bottle orders, inventory sample supplies, and coordinate with Nathan and the state lab to set testing cadence before an anticipated spring startup.