Tri Hydro proposes $220,865 engineering task order for 2026 street improvements

Anaconda Deer Lodge County Commission · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Tri Hydro presented a task order for engineering design and construction oversight priced at $220,865 covering surveys, 60%/95% design and construction administration for 2026 street work; commissioners questioned prioritization of unfinished West Valley streets before approving placement on the agenda.

Tri Hydro engineer Sarah Klein presented a task order for design and construction oversight for the 2026 Street Improvement Project and proposed a fee of $220,865 for survey, design deliverables and construction administration.

“We propose to do that work, for a total of $220,865,” Sarah Klein said during her presentation, outlining replacement work on Spruce, Walnut, Pine and Maple between 4th and 7th streets and work on 8th Street near the courthouse. She said the scope includes design packages at 60% and 95% plus construction quality assurance.

Commissioners asked why the county was moving to work on the courthouse‑area streets while one road in the West Valley (Mountain View North) remained unimproved. Commissioners and staff discussed differing road conditions, the possibility that Mountain View North requires full reconstruction rather than an overlay, and the county’s long‑range plan to rotate work across neighborhoods.

After discussion the commission placed the task order on the agenda for approval; the transcript excerpt records discussion and placement on the agenda but does not include a final voting tally.