Pacific County approves up to $31,000 for extra Tyler Technologies days to complete payroll rollout
Summary
The Board approved a project change request to buy additional Tyler Technologies consultant/project manager days (payroll-specific) not to exceed $31,000 (including tax) from fund 001.034 to support ERP Phase 2 payroll go‑live, scheduled for January 2026.
Get email alerts on the Erp Payroll topic
No spam. Unsubscribe anytime.
The Pacific County Board of County Commissioners approved a project change request Oct. 31 to purchase additional remote consultant/project manager days from Tyler Technologies to complete the county’s enterprise ERP Phase 2 human resources and payroll modules.
The motion authorized expenditure not to exceed $31,000 (including tax) to be paid from the General Current Expense non‑departmental fund number 001.034, subject to adequate budget appropriations. County staff told the board the extra days are needed because the vendor experienced turnover and scheduling delays; the payroll go‑live is expected in January 2026.
The motion passed by voice vote. The public transcript records ayes but does not record an individual roll-call breakdown by commissioner name in the open record.