Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Erp Payroll topic

No spam. Unsubscribe anytime.

Pacific County approves up to $31,000 for extra Tyler Technologies days to complete payroll rollout

Pacific County Board of County Commissioners · October 31, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved a project change request to buy additional Tyler Technologies consultant/project manager days (payroll-specific) not to exceed $31,000 (including tax) from fund 001.034 to support ERP Phase 2 payroll go‑live, scheduled for January 2026.

The Pacific County Board of County Commissioners approved a project change request Oct. 31 to purchase additional remote consultant/project manager days from Tyler Technologies to complete the county’s enterprise ERP Phase 2 human resources and payroll modules.

The motion authorized expenditure not to exceed $31,000 (including tax) to be paid from the General Current Expense non‑departmental fund number 001.034, subject to adequate budget appropriations. County staff told the board the extra days are needed because the vendor experienced turnover and scheduling delays; the payroll go‑live is expected in January 2026.

The motion passed by voice vote. The public transcript records ayes but does not record an individual roll-call breakdown by commissioner name in the open record.