Mantua tables contractor payment amid sewer invoice discrepancy; Well No. 2 needs up to $28,000 more after drive failure

Town of Mantua Town Council · March 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council postponed payment to contractor Twin D over a $42,575 invoice that exceeded prior approvals and heard that Well No. 2 required a $40,000 motor replacement and a $16,095 VFD, with potential additional wiring costs of $12,000–$16,000.

The Mantua Town Council on Feb. 19 voted to table payment to contractor Twin D while staff seeks written approvals and an in‑person explanation for an invoice discrepancy. Public Works Director Marcus Abel reported Twin D billed $42,575 for 11 sewer repairs, exceeding an earlier approved amount of $32,500 for 13 repairs and raising the town’s concern about cost-per-segment increases and possible audit triggers.

Council Member actions: Mayor Pro Tempore Matt Jeppsen moved to table the Twin D payment and Council Member Cheryl Burgan seconded; the motion passed unanimously. The town has requested the contractor appear in person and provide documentation that the extra work was preapproved before authorizing payment.

In a separate infrastructure update, Abel reported a critical equipment failure at Well No. 2. The motor has been replaced at a cost of $40,000; engineers recommended installing a new Variable Frequency Drive (VFD) first (quoted at $16,095.44) to determine whether additional electrical wiring work—estimated at $12,000–$16,000—would be necessary. Abel said the town’s springs and a secondary well currently supply water while Well No. 2 is offline, but staff urged prompt action to restore full capacity before peak summer demand.