Council approves $59,700 change order and deadline extension for 2nd Street waterline project
Summary
The council approved Change Order No. 2 for the 2nd Street waterline replacement, increasing the contract to $1,756,000 and extending substantial completion to Jan. 30, 2026, citing unanticipated buried utilities and additional asphalt work.
City Engineer Philip Bowman told the council that Change Order No. 2 for the 2nd Street waterline replacement addresses additional field quantities the original bid did not fully capture.
Bowman said the original contract award was $1,651,000; a previously approved change order raised the total to about $1,696,000. This second change order increases the contract by $59,700, bringing the contract value to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat