Boca Raton details $1 billion, six-year CIP; $287 million slated for FY24-25
Summary
Financial Services Director Jim Zervos told council the six-year Capital Improvement Program totals roughly $1 billion, with about $287 million proposed for fiscal year 2024-25, funded largely by locally generated revenue and including major utility and transportation projects.
Get email alerts on the Capital Investment topic
No spam. Unsubscribe anytime.
Jim Zervos, the city's financial services director, presented a six-year Capital Improvement Program that includes roughly $1 billion in projects and about $287 million planned for fiscal year 2024-25.
Zervos said the plan spans heavy infrastructure, vehicles and equipment and ties to council strategic priorities. "If you look at a timeline over the 6 years, you'd see about $287,000,000 of that is actually planned for this next fiscal year, 2425," he said. He told council the CIP is a planning document that covers projects that often span multiple fiscal years and that the department-specific breakdowns show large investments in municipal services and utility services.
Zervos reviewed major categories and example projects: municipal services (government campus master plan, downtown walkability improvements, Sanborn Square renovations), transportation (Jeffrey Street railroad crossing expansion, NW/SW 4th Avenue widening), public safety technology upgrades and water and sewer rehabilitation and wastewater-treatment facility improvements under utility services.
He said top funding sources are locally generated (utility-related revenues, a $31 million revenue bond tied to sanitation, general fund contributions and building-permit revenue) and emphasized the city's low-debt posture and a triple-A rating. "We have very little debt in the city, and that's a good thing," he said, adding that bonds would be considered primarily for long-lived heavy infrastructure projects.
Councilors asked about bond practices and the timing of projects; Zervos said detailed discussions would precede any bond issuance and that some projects will span multiple years and out-years of the plan. The CIP and operating budget will return to council in September with more detailed project budgets.