Commissioners report Chabok Road solar facility construction under way, three-month timeline estimated
Summary
Members reported material on site and an anticipated roughly three-month construction timeline for the Chabok Road solar facility; Eversource coordination will be required to complete the interconnection and switch-on.
Get email alerts on the Local Solar topic
No spam. Unsubscribe anytime.
At the Aug. 28, 2025 Energy Commission meeting, commissioners reported progress on the Chabok Road solar facility. Vice chair Chris Bandasian described seeing material on the ground and estimated roughly a three-month construction timeline before the town and contractor coordinate with Eversource to complete interconnection and "throw the switch."
Commission members said the timing will intersect with the town—udget season and that coordination with Eversource will be required after construction to complete the operational steps. Gene Walker noted the next steps include Eversource scheduling for final commissioning once the contractor completes work at the site. No formal vote or additional funding was requested during the update; commissioners celebrated the project—reakthrough and thanked past and present participants.