Town staff reported the Chobock Road solar facility transformer has arrived, fencing and jersey barriers are in place, final inspections and third‑party testing are scheduled and Eversource interconnection/testing may take about eight weeks once test results are submitted.
Town staff updated the Energy Commission that work at the Chobock Road solar facility is progressing and the long‑lead component that had delayed activation — the transformer — has arrived.
Assistant Town Manager Jean Walker showed photos of the array and the newly placed transformer and explained that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans