Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Aberdeen board pledges local match for two federally funded sidewalks, approves Carbon Reduction project submittal
Summary
The Town Board unanimously approved Resolution #25-06 to support committing the 20% local match for two sidewalk projects on Poplar Street and Johnson Street and authorized submitting a Carbon Reduction Program application for an additional segment tied to the Poplar Street project.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Aberdeen Town Board on April 14 unanimously approved a resolution committing the town’s required 20% local match for two bicycle and pedestrian projects that are funded through the NCDOT State Transportation Improvement Program (STIP).
Planning Director Pam Graham told the board the two projects—an eastern-side sidewalk on Poplar Street from Johnson Street to Aberdeen’s jurisdictional boundary near Blue’s Crossing Apartments and a Johnson Street sidewalk from Southern Middle School toward U.S. 15/501 connecting to existing sidewalk at Moe’s—were originally submitted in 2014 and carried into the 2024–2033 STIP after delays. Graham said the town’s 20% share would be payable over five years and described the total current estimates for the two segments as approximately $400,000 (Poplar Street) and $330,000 (Johnson Street).
Graham said the projects are a “great opportunity to get sidewalks at an affordable cost,” and the board voted 5–0 to adopt Resolution #25-06 supporting the local match.
Town Manager Paul Sabiston also asked the board to authorize submitting a Carbon Reduction Program project to the Sandhills Metropolitan Planning Organization (SMPO). Sabiston said the Carbon Reduction application must be for a project on a state highway and recommended tying a short additional Poplar Street segment to the sidewalk project to strengthen the submittal. He noted the SMPO program requires a 20% match and that roughly $300,000 in program funds were available regionally, with an estimated $50,000 potentially available to Aberdeen depending on awards.
The board voted unanimously to authorize staff to submit a Carbon Reduction project application.
What happens next: staff will prepare detailed cost estimates and formal submittals for both the STIP match process and the SMPO Carbon Reduction application; Graham said right‑of‑way and utility phases are scheduled to begin this year. A public hearing for other planning items, including a UDO text amendment, is set for April 28, where related planning matters will be discussed further.
