Kossuth County advances drainage projects: $1.73M low bid for DD 4 Lat 11, pay application and change order approved for JDD PAK 1

Kossuth County Board of Supervisors · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Kossuth County Board of Supervisors approved a $1,730,588.75 low bid for DD 4 Lat 11, approved Change Order #1 (+$1,178) and Pay Application #1 ($126,892.72) for JDD PAK 1 in a joint teleconference with Palo Alto County, and voted to notify landowners about pending litigation (Case #EQCV027965) related to DD 4 Lat 11.

Kossuth County took multiple drainage actions March 17, advancing construction and administration for several drainage districts.

The board approved the low bid from Reutzel Excavating on Alternate 2 for DD 4 Lat 11 Improvement in the amount of $1,730,588.75; the motion carried unanimously. The board also voted to notify landowners regarding the lawsuit in Case #EQCV027965 on DD 4 Lat 11 and to include a full copy of the judge’s decision and the appeal to the Iowa Supreme Court filed by the plaintiff in the notification.

In a joint teleconference with the Palo Alto County board, Kossuth County approved Change Order #1 for JDD PAK 1 increasing the contract by $1,178.00 and approved Pay Application #1 to Reutzel Excavating, Inc. for $126,892.72; both motions carried unanimously by both boards.

The board acknowledged a petition from MJF Trust to use an outlet in DD 116 and directed engineering firm Bolton & Menk to obtain further information at the landowner’s cost. The board accepted the Engineer’s Report for DD 80 Lats 10 & 70 and the Commissioner’s Report on DD 4 Lats 40 & 42, and set multiple public hearings for May 26, 2026, on DD 80 and DD 4 lat improvements.

These approvals move several projects toward construction and require notifications and further public hearings; the minutes do not include construction schedules or detailed timelines beyond the hearing dates and payment amounts recorded.