The City of Lewistown approved a $55,000 emergency contract with Griffith Construction to replace a half-block of sewer line near the Civic Center after staff discovered severe infiltration and were unable to camera or clear the pipe.

The City Commission of Lewistown voted to award a $55,000 emergency contract to Griffith Construction to replace approximately a half-block of sewer line near the Civic Center.

City Manager Holly Phelps told the commission that "late fall, we discovered about a half a block of sewer line that had extreme red infiltration," and staff were unable to camera or clear the line before soliciting emergency bids. Phelps said only one contractor submitted a bid and the citys engineers judged the price to be fair.

Commissioner Terry moved to approve the purchase/construction order for the emergency sewer line replacement; Commissioner Bueller seconded. The motion passed on a roll-call vote with six ayes and one absent.

The contract was described to cover the localized emergency repair; commissioners asked whether the work had already started and were told crews were "gearing up" to begin. The city will monitor the repair schedule and related invoices through the project completion.

The commission's action authorizes the city manager to proceed with the contractor on the scope and price presented. The item concludes Lewistowns immediate repair plan while staff continue inspecting the broader system.