Library renovation team finds corroded chiller pipes; AFC warned of possible $100k-plus repair
Summary
AFC received construction updates on the Memorial Hall library renovation: a faulty main power switch will use contingency funds and rusted chiller pipes were discovered—engineers say replacement could consume a large portion of contingency, with preliminary estimates described as 'a couple $100,000'.
Get email alerts on the Library Renovation topic
No spam. Unsubscribe anytime.
Committee liaisons reported that the library renovation has uncovered two technical issues: a main power switch that did not fully shut power (a modest fix to be paid from contingency) and, more seriously, external corrosion on chiller pipes that carry the cooling/water for the HVAC system. "They're rusty," the liaison said, and engineers found compromised connections where pipes join, raising concern about long-term leaks and durability.
The project’s owner’s project manager and engineers are collecting quotes and options. Initial comments in the meeting suggested replacement could be "a couple $100,000 or so" and would use a significant portion of contingency funds; demolition pricing and more detailed replacement estimates are still pending. Committee members stressed that now — while interiors are exposed — is the appropriate time to address the issue to avoid reopening the building later.
Members asked about schedule impacts and were told the OPM is pushing to keep the overall completion target (reported as August) and that, so far, the work remains on schedule; however, the committee may need to convene an extra meeting if a formal vote on contingency spending is required. The AFC noted the OPM has in some cases rebid or adjusted scope (example given: bookcase removal costs dropped when done on time-and-materials instead of fixed price).