Fall River board approves referendum contracts, outlines $9.85M project plan
Summary
The Fall River School District board approved consultant and contractor contracts and advanced referendum implementation tied to the $9,850,000 capital referendum, setting a user-group schedule, a February resolution to seek bonds and a construction timeline targeting spring 2025 start and 2026 completion.
The Fall River School District board approved construction-management and professional services contracts and reviewed a phased plan to spend the $9,850,000 authorized by the district’s recent capital referendum.
The board heard from Aaron Dutz of the construction manager (Bendort/Fendorp), who described the contract as a standard AIA cost‑plus construction‑management format and said "any unused contingency would go back to the district." The board also heard from PRA (architect) about schematic and design phases, user‑group meetings and a target to break ground in spring 2025 with completion aimed for 2026.
Why it…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat