Madeira outlines timeline for Miami, Laurel and Camargo road projects
Summary
City staff told council on Feb. 23 that Miami Avenue work is continuing while utility pole work finishes, Laurel Avenue construction starts in March and should last about three months, and Camargo Road bidding begins late March with work expected before end of 2026 lasting about six months.
City staff provided an update on several upcoming street projects at the Madeira City Council meeting on Feb. 23.
Dr. Alicia Camper described the Miami Avenue project as continuing while one vendor completes work related to lines remaining on electric poles. She said Laurel Avenue work is slated to begin in March and is expected to continue for about three months. Camargo Road is in phase one; bidding is planned to begin at the end of March, and staff said the goal is to begin construction before the end of 2026 with work lasting approximately six months.
No formal vote was recorded on project schedules; the timeline and procurement steps described were presented as project updates. Specific contract awards, budgets and start dates for Camargo Road were characterized as contingent on bidding outcomes and were not specified in the minutes excerpt.