Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Library Construction topic
No spam. Unsubscribe anytime.
Board approves 10 change orders for La Crosse Public Library construction
Summary
The Board of Public Works unanimously approved 10 construction change orders for the La Crosse Public Library, covering items such as asbestos abatement, electrical routing changes, added floor boxes, a hearing‑loop installation and related floor leveling (item 25-1434).
Get email alerts on the Library Construction topic
No spam. Unsubscribe anytime.
The Board of Public Works unanimously approved 10 construction contract change orders for the La Crosse Public Library at its Dec. 15 meeting. The board recorded the agenda item as 25-1434 before voting.
Director Dawn Wasek of the La Crosse Public Library summarized the changes for the board. “So we have, 10 change orders,” Wasek said, then detailed items including a split cost for a folding‑partition fabric spec inconsistency and additional plumbing piping required after a building‑inspector code interpretation.
Wasek told the board the work includes additional demolition where existing walls were CMU or poured concrete rather than stud framing; asbestos flooring abatement in several areas; door frame and hardware modifications to match existing doors; and ceiling coordination that produced a credit because more of the ceiling could be retained.
She said the project also adds and removes floor boxes (to improve new‑floor installation and to support computer-table power), revised the routing path for an electrical panel feed where concrete beams conflicted with the original route, and switched the hearing‑loop design to an underfloor system for more consistent coverage in the masonry room. “We had to add a couple of floor boxes for the computer tables based on coordination with the furniture supplier,” Wasek said.
The change that followed the hearing‑loop decision required leveling and a skim coat to prevent the hearing loop from telegraphing through the LVT flooring; Wasek said flooring and AV suppliers recommended that approach. She also described mold‑related framing adjustments and a handful of plumbing and fixture clarifications.
There were no further board questions before the chair called for a vote. The board approved the package of change orders unanimously. The chair noted the item number for the record as 25-1434.
The approval covers the listed construction adjustments; the meeting record does not provide line‑item dollar totals in the transcript. The next procedural step is implementation through the project contractor and corresponding contract documentation.
