North Haledon engineer reports delays and upcoming paving for borough road program
Summary
Borough Engineer Joseph Pomante told the council the Overlook/High Mountain signal hardware has no firm delivery date, Linda Vista is nearing closeout, Squaw Brook award is on the agenda, and the 2025 road program will begin milling and paving in about two weeks.
Get email alerts on the Road Projects topic
No spam. Unsubscribe anytime.
Borough Engineer Joseph Pomante updated the North Haledon council on Oct. 15 about the borough's road work schedule and project status. Pomante said signal hardware for the Overlook Avenue/High Mountain Road intersection has no firm delivery date, Linda Vista Avenue work is being closed out, and the Squaw Brook Road Improvements project is listed on the agenda to be awarded. The 2025 road program is currently doing concrete work, with milling and paving expected to begin in roughly two weeks. An upcoming NJDOT meeting should clarify timing for a FY2026 Municipal Aid grant for Highland Road.
The engineer was dismissed by Mayor Randy George at 8:00 p.m. The transcript does not record final contract awards or appropriation votes during this work session; some items (including an award for Squaw Brook Road Improvements) appear on the consent agenda and would require formal action at a meeting where votes are recorded.