Coweta City Council · February 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Manager Julie Casteen reported scheduled groundbreakings for the police (Feb. 5) and fire (Feb. 11) stations, ongoing Skyview water-tower interior sandblasting with weather delays, groundwater issues slowing work on 257th E Avenue (Midway Road), and completion of sludge removal from the water-treatment-plant lagoon. Contractors will rehabilitate the dam when weather allows.

City Manager Julie Casteen briefed the Coweta City Council on several capital projects at the Feb. 2 special meeting.

Casteen said the groundbreaking for the new police station is scheduled for Thursday, Feb. 5, 2026, and the fire-station groundbreaking for Wednesday, Feb. 11, 2026, though both dates are subject to change because of weather. She told the council the Skyview Water Tower interior is being sandblasted: crews have completed the entire floor and bottom ring and are working on rings 2, 3 and 4 in sections roughly 40 feet wide. Cold weather and heavy snow forced a temporary pause; work resumed on Jan. 28.

Work on 257th E Avenue (Midway Road) has progressed to removing material from the northbound lane and shaping the ditch and street base, but contractors encountered significant groundwater seeping to the surface; Casteen said the site will be reevaluated once weather improves to determine necessary revisions for construction to continue.

Casteen reported sludge removal from the water-treatment-plant holding pond has been completed and testing at random locations confirmed acceptable removal levels. The next step is dam rehabilitation, which will involve trenching and installing a barrier to prevent leakage; that work is paused due to weather.

Casteen also reviewed the Oklahoma Municipal Assurance Group (OMAG) 2025 stewardship reports; no council action was taken on those reports at the meeting. Mayor Naomi Hogue and Vice Mayor Jeremy Barnett both praised city crews for their winter-storm response during the meeting.

Council did not take action on project dates or contract changes during the session; staff will return to council with updates as conditions change.