Summary

Superintendent Evan Cardwell and Maintenance Director Joe Hernandez told the board the district’s 2023 bond projects are approximately 88% complete and listed remaining work including roofing, gym siding, parking lots, batting cages, HVAC and campus cameras.

Superintendent Evan Cardwell and Maintenance Director Joe Hernandez updated the Calhoun County ISD Board on the status of projects funded by the district’s 2023 bond program on Feb. 23.

The report listed work across district campuses: the Ag barn; Calhoun High School (bus lane canopy, gym II metal siding and gutters, baseball field parking lot, baseball and softball batting cages); Hope High School (front and back parking lots); HJM (back parking lot); Seadrift School and JR Elementary (gym window infills); Seadrift School (gym siding, main building and dressing room roof); HVAC upgrades at the district support center; and installation or upgrades to campus camera systems. The minutes state the bond program is approximately 88% complete.

Board members did not take formal action on the bond update; the item was presented as information. The minutes do not include a project schedule or remaining cost estimates.