Adair County signs Harrison Bridge contract, approves right-of-way payments and sets road-vacation hearing
Summary
The board signed a contract and performance bond for the W18 Harrison Bridge project, approved two right-of-way payments of $851.14 each for the NW20 Grand River culvert project, and set a public hearing for vacating part of 115th Street for March 11, 2026 under Iowa Code Chapter 306.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Adair County Board on Feb. 11 authorized county staff to sign the construction contract for the W18 Harrison Bridge Project (L-LBRW18H—73-01) and approved the related performance bond. The board also approved right-of-way contracts for the NW20 Grand River RCB Culvert Project (L-LRCBNW20GR—73-01), authorizing payments of $851.14 each to Stan and Denise Herrick and to Joseph and Molly Herrick.
Separately, the board approved Resolution No. 2026-17 to set a public hearing on vacating a portion of 115th Street (established April 3, 1877) in Section 9, T-77N, R-30W; the hearing is scheduled for 9:15 a.m. on Wednesday, March 11, 2026 in the Adair County Courthouse in Greenfield in accordance with Iowa Code Chapter 306.
County Engineer Nick Kauffman also provided a maintenance and activities update, noting discussions about rock prices and updates to projects tied to the urban renewal plan. Kauffman exited the meeting at 9:18 a.m.
The minutes record motions and approvals but do not include contractor names beyond the project codes or additional project schedules and timelines.