Committee awards $1.39 million maximum contract for parking-structure repairs

Finance Committee · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Finance Committee approved awarding Unit S-266 parking-structure repair work to Western Specialty Contractors for $1,006,918.50 with a 15% contingency ($181,000), totaling not to exceed $1,387,718.50; staff said competitive bids and unknown site conditions justify the contingency.

The Finance Committee unanimously approved Jan. 12 an award to Western Specialty Contractors for Unit S-266 parking-structure repair and preventative maintenance. The base contract amount is $1,006,918.50 with a 15% contingency ($181,000) for a project total not to exceed $1,387,718.50. The motion passed 5-0.

The committee's deputy director for public works explained that bids were competitive and that contingencies address unforeseen conditions that can appear once contractors begin concrete removal and other on-site work. "DPW staff are happy to report that we continue to see increased interest, with hungry bidders," the deputy director said, and described the contingency as a practical allowance: "It's a little bit like surgery where sometimes you get in there... and it's then when you really get a even a better sense" of additional work needed.

Committee members did not request amendments to the award. The transcript records a motion to approve and a second and then a voice vote approving the contract, 5-0. No additional funding sources or schedule details were specified in the meeting record.