Committee approves sole‑source procurement for city‑hall emergency notification system

Human Resources & Information Technologies Committee · January 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Committee approved spending up to $30,000 (CIP budgeted at $35,000) to procure a duress/emergency notification system for city hall via a sole‑source vendor; the presenter cited a $25,695 vendor quote plus a 15% contingency and noted the same vendor installed the system at the Appleton public library. Vote: 4-0.

The committee approved a sole‑source procurement request to install an emergency notification (duress) system at city hall.

A director told members the 2026 CIP included $35,000 for the project and asked the committee to release $30,000 to begin procurement. The presenter said a vendor quote of $25,695 plus a 15% contingency underlies the $30,000 request and that the police department and human-resources risk manager participated in system testing and selection. He also said Nielsen Communications (NCI) — the vendor that installed the same system at the Appleton Public Library — would be used for the work, which is among the reasons the request was characterized as sole source.

“We did a couple other tests with some other systems...this was really the system that it came down to,” the presenter said, explaining police recommendations and prior local installations informed the procurement approach.

Committee members had no further questions and approved the expenditure by voice vote; the presenter and chair recorded the action as passing 4 to 0.

Staff said procurement would proceed under the purchasing manager’s approval and that final contract terms and implementation timelines would be reported to the committee as the work advances.