Valley Transit board approves TransTrack extension, router purchase and RDR commissioning contract
Summary
The Valley Transit Board approved an extension and new modules for its TransTrack data system (including certification of automatic passenger counting), authorized a router-and-antenna purchase, and awarded a commissioning-agent contract for the Whitman Phase 2 project. Financial totals and bid amounts were presented during voice votes.
Get email alerts on the Procurement Contracts topic
No spam. Unsubscribe anytime.
The Valley Transit Board voted to approve a set of vendor contracts and routine payments at its March meeting, including an extension of the agency's data-management system and certification work for automatic passenger counting (APC), approval of new routers and antennas for buses, and a commissioning-agent contract for the Whitman Phase 2 facilities project.
Board members moved and approved the items on voice votes after staff presentations. Dave, a transit staff member who led procurement presentations, said the two TransTrack projects together carry a one-year price of $132,590 and "the total 8 year cost is just over, it's almost $734,000," and recommended an eight-year contracting approach with termination rights if work is unsatisfactory. "TransTrack is our current data management system...they've done this for other transit systems," he said, adding the APC certification requires a qualified statistician and a new database module to cleanse counts so ridership sensors can be used for federal reporting.
The board also approved a router-and-antenna purchase for the agency's fleet, with the memo citing a project cost of $82,238. The transcript shows the memo identifies a low quote from a vendor called "Bacom" and also states the recommendation to award to "AECOM." The record contains this inconsistency; the Board approved the purchase as presented. (The vendor naming in the meeting transcript is inconsistent and is noted for verification in procurement records.)
For the Whitman Phase 2 facilities contract, Ron Torrance described two bids for a commissioning agent: RDR at $27,600 and IMEG at $49,600. Staff recommended awarding to the low bid, RDR, with a 5% contingency for a not-to-exceed amount of $28,980. The board approved that award on a voice vote.
Routine payments and the minutes were also approved earlier in the meeting on voice votes without a roll-call tally. Chair-led motions were seconded and carried with members saying "aye"; the transcript records no named roll-call vote tallies.
The approvals move forward three procurement steps for Valley Transit: finalizing TransTrack's expanded scope and APC certification so the agency can report federally certified ridership, replacing aging routers and antennas on vehicles, and securing third-party MEP commissioning oversight for an ongoing capital facility project. The board did not record any substantive dissent during the motions.
Next steps: staff will execute the approved contracts and return to the Board if amendments or contract changes are required. The Board's next regular meeting is scheduled for March 24.