LAUSD proposes Central Manufacturing Kitchen in Bell to deliver fresher meals, consolidate Newman operations
Summary
LAUSD staff proposed studying a Central Manufacturing Kitchen at the Slauson Southeast Occupational Center/Bell Storage Yard to serve about 170 Newman sites (roughly 60,000 students), funded in part by Measure US and planned for a multi‑year delivery timeline.
Get email alerts on the School Nutrition topic
No spam. Unsubscribe anytime.
LAUSD facilities and food‑services staff presented a proposal to study and potentially build a Central Manufacturing Kitchen (CMK) to centralize meal production, increase fresh food preparation, expand local sourcing and create culinary training and apprenticeship opportunities.
“As we identified in the 2024 food services master plan, we need a new CMK to support fresh, healthy, and appealing meals,” said Dr. Deborah Bryant, acting chief of school operations. Facilities staff said Measure US included an allocation (presentation cited $240 million within the bond category) to develop a kitchen to prepare fresher student meals and support district sustainability goals.
Asam Bridal, director of facilities planning and development, said the proposed lead site for further study is the Richard Slauson Southeast Occupational Center and the adjacent Bell Storage Yard, which together offer roughly 4–5 usable acres, close proximity to major transportation corridors and synergy with DACE culinary programs.
Manish Singh (director of food services) and other staff said the CMK would consolidate packaging and add cooking capacity that the current Newman Packaging Center lacks. Singh argued that a CMK would enable more scratch or “speed‑scratch” preparation, greater control over recipes and quality, and potential cost advantages from increased local procurement and bulk preparation. He said the CMK would create new full‑time positions and allow some existing Newman staff to move into 8‑hour jobs at the new facility.
Facilities explained next steps: the district plans to ask the board to authorize a site analysis contract with an architect and kitchen specialist (expected next month); staff said that test‑fitting, programming and a preliminary project definition would take roughly 5–7 months, with a return to the board for project definition by December 2026 and a typical 4–5 year schedule from design to construction if approved.
Board members asked about the scope and the $300 million vs $240 million figures referenced in recent materials. Christina Tokes, chief facilities executive, explained that the larger figure includes indirect costs and program reserve set aside across the bond program; the presentation allocated $240 million to the kitchen after standard reserves and indirects were accounted for.
Public commenters and some board members asked for stronger community engagement, ROI analysis and data on food quality and participation; a public speaker noted concerns about land history and asked for careful review of the site and potential regional partners. Staff said environmental review, DSA approvals and coordination with the city where off‑site improvements are needed will be part of the next stages.
No board vote was taken; staff will return with a recommendation to authorize a site analysis and a more detailed project scope and cost estimate.