Matthews accepts $466,000 disaster‑relief reimbursement and approves $560,000 budget amendment for Devore Dams work
Summary
The board authorized execution of a memorandum of agreement for a $466,000 reimbursement grant and approved a $560,000 budget amendment (including 20% contingency) to begin preconstruction and design to bring two town-owned dams into compliance with North Carolina dam-safety requirements.
Get email alerts on the Infrastructure Dams topic
No spam. Unsubscribe anytime.
The Board of Commissioners on March 23 authorized the town manager to execute a memorandum of agreement to accept a $466,000 reimbursement grant from a disaster relief and mitigation fund and approved a $560,000 budget amendment to begin preconstruction and design work on Devore Dams (a town-owned pair of dams at 3221 Chippewood Lane).
Staff described the history: the town purchased the property in 2022, hired an engineering firm to produce an inundation study and emergency-action plan, and after heavy rainfall during Tropical Storm Debbie the state issued a notice of deficiency (NOD) that identified the dams as not meeting the state’s probable-minimum-precipitation standards. "We received notice last month that our disaster relief and mitigation fund grant was selected for funding," staff member Fitzpatrick told the board and asked for authorization to accept the grant and to approve preconstruction funding.
The requested $560,000 budget allocation covers preconstruction and design activities and includes a 20% contingency. Commissioners voted unanimously to authorize the town manager to accept the reimbursement grant and to approve the budget amendment.
Why it matters: the work is required by state dam-safety rules following the NOD; the board’s action funds the next phase so staff and engineers can design repairs and comply with regulatory requirements.
Next step: staff will move forward with preconstruction and design procurement and report project milestones and contract awards to the board.