Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Emergency Response topic

No spam. Unsubscribe anytime.

Ventnor officials tally storm response after Feb. 21–26 snow event; crews credited for quick work

Ventnor City Board of Commissioners · February 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported 92 tons of road salt used, roughly 4,000 pounds of ice-melt, 22 broken water meters replaced, 745 overtime hours and more than 100 truckloads of snow removed during the Feb. 21–26 storm; commissioners praised public works and first responders.

Commissioners and staff reviewed Ventnor’s multi-department response to the Feb. 21–26 snowstorm, calling the event labor-intensive and noting that crews stabilized critical infrastructure.

Public works reported using 92 tons of road salt and roughly 4,000 pounds of sidewalk ice melt, replacing about 22 broken water meters and logging 745 overtime hours across 16 workers. Crews removed approximately 102 dump-truck loads of snow from intersections and completed 32 residential driveway assists and eight medical-assist resident transports. The police and fire departments increased staffing and the fire department recalled additional personnel; the city reported roughly 40 calls for service related to the storm.

Officials thanked public-works and emergency crews for rapid response and said debris, downed wires and some localized pump-station outages were addressed quickly, noting coordination with Atlantic City and state liaisons for assistance.