Summary
At the Jan. 15 work session Borough Engineer Joseph Pomante reported NH-750 (Molly Ann Pump Station Rehabilitation) is in the reimbursement phase with final payment applications submitted to the state (payment expected April–May), NH-760 awaits signal equipment, NH-823 grant award is pending, Squaw Brook pre-con is scheduled, and 2024 road program punch-list work is planned for spring; pickleball courts and Willow Field work are slated for spring.
Borough Engineer Joseph Pomante presented the engineering report at the Jan. 15 work session, summarizing capital-project status and near-term scheduling.
NH-750 (Molly Ann Pump Station Rehabilitation) is in the reimbursement phase: final payment applications have been submitted to the state and Pomante said the project should be closed out in April or May when payments arrive. Mayor Randy George requested scheduling a time for council members to tour the new sewer plant once the project is closed out.