Plainview ISD hears costs, compliance plan for state 3‑point seat‑belt mandate on school buses
Loading...
Summary
District transportation staff and First Student estimated retrofitting noncompliant buses would cost about $25,000–$35,000 per bus; with 16 noncompliant route buses, retrofit estimates approached $480,000. The board approved a phased replacement and adoption of district policy steps to comply with the state mandate by the September 1, 2029 deadline.
District and contractor representatives briefed trustees on Senate Bill 546 (as presented) and the district’s plan to meet new requirements for three‑point seat belts on school buses.
Transportation background and scope: District staff reported a fleet of 34 route buses: 18 currently compliant with three‑point seat belts and 16 noncompliant. A First Student representative introduced during public comment advised retrofit quotes range from roughly $25,000 to $35,000 per bus depending on age and interior configuration. At that estimate, retrofitting 16 buses would cost about $480,000.
Phased replacement vs. retrofit: First Student and district staff recommended phasing in new compliant buses as buses reach end of life rather than immediately retrofitting older vehicles, noting many noncompliant buses are near the end of their service life and the statutory compliance deadline is Sept. 1, 2029. The vendor noted nine buses in the current contract were already scheduled to be replaced as part of normal fleet turnover, with additional buses to be accelerated as needed.
Policy and enforcement: Staff said the district will likely need updated student‑transportation policies (including parental signatures on bus‑riding agreements) and discipline provisions to enforce seat‑belt use. The district plans to return to the board with policy language and a timeline for phased expenditures and TEA reporting should the board confirm the approach.
Board action and next steps: Trustees voted to adopt the TASB/board approach to comply with the law and accepted the phased plan and contractor recommendations; staff will draft policy language, finalize cost projections, and return with more detailed spending plans and TEA reporting as required.
Direct quotes from the meeting were limited; cost ranges and the 34‑bus fleet count were provided by First Student representatives and district staff. The board did not approve immediate full retrofits at the meeting but endorsed the phased replacement approach and signaled follow‑up work on policy and budgeting.