Airport staff report taxiway bid timing, MTSU permitting progress and remaining work on hangars and water project

Municipal Airport Authority Board ยท March 24, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said taxiway/run-up pad work should go to bid in early February, MTSU site permitting is close to clearance from TDEC, shade-ports and a corporate hangar are being finalized for spring bidding and two hangars under construction await concrete/asphalt work.

Airport staff provided a construction briefing that covered multiple projects at Shelbyville Municipal Airport.

On airfield work, staff said they plan to advertise the taxiway and run-up pad for bid the first week of February; the project is tied to a larger layout for future hangar development. Staff also said final design steps for a federal tower application are ready pending a TDOT meeting and that FAA planning delays at the Memphis ADO have slowed some reviews.

The MTSU project has had permitting delays but staff reported that the SWIP (stormwater) construction-general permit resubmission had been accepted and TDEC was conducting a review expected to conclude the following week. Demolition items were complete (old house, barn, seed separator) and the airport has coordinated salvage/donation of an antique seed separator to a local museum.

Two hangars under construction have metal erected but await concrete or asphalt work; staff said work may be delayed by cold-weather constraints or asphalt-plant availability. The water project is functionally complete but not fully paid; staff noted follow-up plumbing connections remain to be scheduled and that some small scope items will be addressed during later contractor work.

Staff also confirmed that shade ports and a corporate hangar package is being finalized for a March bid to meet TDOT funding deadlines. The board asked staff to continue coordinating grant timelines and to present firm bid dates and project cost estimates when available.