Airport staff report taxiway bid timing, MTSU permitting progress and remaining work on hangars and water project
Summary
Staff said taxiway/run-up pad work should go to bid in early February, MTSU site permitting is close to clearance from TDEC, shade-ports and a corporate hangar are being finalized for spring bidding and two hangars under construction await concrete/asphalt work.
Airport staff provided a construction briefing that covered multiple projects at Shelbyville Municipal Airport.
On airfield work, staff said they plan to advertise the taxiway and run-up pad for bid the first week of February; the project is tied to a larger layout for future hangar development. Staff also said final design steps for a federal tower application are ready…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat