Council authorizes advertising bids for Mesa Water Project contingent on state approval

City Council · March 30, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized staff to advertise bids for the multi-phase Mesa Water Project after a consultant presented design, hydraulic modeling and a plan to drill six wells in phase two; advertising will proceed after DEQ permits and staff expects DEQ action within about 30 days.

The city council authorized staff to advertise bids for the Mesa Water Project contingent on regulatory approval after a detailed presentation by the project consultant.

Consultant Crystal Floyd introduced the three-phase project: phase 1 (completed test wells), phase 2 (well-field development with six planned wells) and phase 3 (transmission line and booster station to tie the new supply into the existing system). Floyd said the estimated production per well is "between 3 and 5" as reported in the transcript; the record does not state units or the precise measure (staff said final production will be confirmed by full-scale pumping tests after drilling).

Floyd described easements already acquired for well sites, access roads, collector lines, electrical service and fiber communications, and she said the design includes SCADA and operational controls. She also explained the project's hydraulic model, which staff used to size piping and select the booster-station site to manage pressure zones and friction losses.

On schedule and permitting, Floyd said the project application was submitted to the state environmental regulator (referred to in the transcript as "DEQ" and in other lines as "ODEQ"); she said the regulator is allowed a 45-day turnaround but staff is hoping for action in under 30 days so the city can proceed to advertise for bids. The city manager and council praised staff and partner agencies and said, if schedule holds, they expect water delivery around July 2027.

A motion to authorize advertising for bids on the Mesa Water Project was moved, seconded and approved by voice vote; the transcript records council members Sanchez, Helton and Peterson voting "aye." The authorization was expressly contingent on obtaining the required regulatory approvals before issuing bid advertisements.

What happens next: staff will monitor the DEQ review and, after receiving regulatory clearance, will advertise the project for competitive bids per council authorization. Final production numbers, pump sizes and contract awards will be set after drilling, testing and bid evaluation.

Notes and clarifications in the record: the transcript records the consultant's production estimates without units and uses different spellings for DEQ/ODEQ; these points should be confirmed in staff documents before publication of specifications or the bid packet.