Eddy County details $11.1 million spring–summer road program covering about 68 miles

Eddy County Commission · March 24, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works presented a spring/summer 2026 road plan covering approximately 68 miles at an estimated $11.1 million, describing treatments such as reclaim and double pin chip seals, a widening of Derrick Road, and phased microseal follow-ups to extend pavement life.

Eddy County Public Works presented an alphabetized spring/summer 2026 road-maintenance and improvement list that will cover about 68 miles at an estimated cost of $11,100,000.

The presenter described a mix of treatments selected by road condition and traffic: full reclaim and rebuild where needed, double pin chip seals followed by microseals a year later to preserve pavement, and targeted asphalt paving at intersections that have failed under chip-seal approaches. "In conclusion, we have 68 miles road prepared for the spring and summer this year at a cost of 11,100,000.0," the presenter summarized.

Specific work called out included Brantley Road (about 9.9 miles; estimated 10 days and roughly $127,000), double pin chip-seal and widening on Carrasco Road to complete truck-route connectivity, and a two-foot widening on each side of Derrick Road with a 2-inch asphalt shoulder and subsequent full paving across the road. Staff explained timing constraints for chip sealing (ground temperatures consistently at 60°F) and the need to sequence double pin then microseal to extend life.

Commissioners asked about spot widening of a narrow bridge approach and whether concrete approaches should be studied at some intersections instead of asphalt; staff agreed to look into design alternatives. The presentation included a pledge to preserve unpaved roads and maintain pothole crews for emergent response.

What happens next: staff will proceed with procurement/contracting steps on the identified projects, return with schedules as seasonal windows open, and explore concrete approach options where commissioners requested further study.