Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Commissioners authorize 'not to exceed' change order to add irrigation to historic courthouse grounds project

Lincoln County Board of Commissioners · March 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Lincoln County commissioners approved authority for a change order to add an irrigation system back into the historic courthouse landscaping project to avoid rework; staff said the final cost should be well below $80,000 and an initial allowance was $22,007.40.

The Lincoln County Board of Commissioners authorized county staff to approve a change order to add an irrigation system to the historic courthouse grounds project, aiming to install the system before sod is laid to avoid tearing up finished landscaping.

Josh Grant told the board that irrigation had been value-engineered out of the project earlier but that the project’s landscape architect recommended a simpler perimeter system rather than a complex drip-line. He said the county put a 'not to exceed' amount in place so the chairman could sign the change order when the final quote arrives.

Grant said the original allowance before value engineering was $22,007.40 and the project team expects the final price to be well below $80,000, though he could not give a definitive number at the meeting. The work includes concrete cutting and re‑finishing and extended general-contractor time on site; the total schedule for sleeving and system installation is roughly four weeks according to the contractor estimate.

Commissioners expressed a desire to see the estimate come down toward the earlier allowance but supported moving forward so the schedule for laying sod and opening the grounds is not delayed. The board approved the motion to allow the change order to proceed on the stated 'not to exceed' basis and asked staff to keep the cost under $80,000 and return with final documentation as needed.