District outlines repair and replacement plan for glycol leak, chillers and boilers using escrow/bond funds

Perkiomen Valley School District Safety and Operations Committee · March 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Operations reported a broken glycol pipe under the Schwenksville building with a repair estimate of about $100,000, and recommended using escrowed interest and remaining 2019 bond funds (about $536,000 identified) to replace chiller pumps (~$90,000) and a backup boiler (~$306,000); staff noted insurance coverage is under discussion.

Operations staff described several facility maintenance needs and a recommended funding approach at the committee meeting.

Mr. Fabrizio reported crews found a broken 8‑inch glycol pipe under the Schwenksville building; contractors used acoustic methods to locate the leak, excavated and cut two pipe sections, and plan to weld and reinstall new sections. He estimated the repair at approximately $100,000 and said insurance involvement is under review.

Separately, counsel (Fox Rothschild) and staff identified roughly $536,000 in escrow interest funds restricted to escrow‑related expenses; staff proposed using those remaining escrow funds, along with 2019 bond funds, to replace older chiller pumps (~$90,000) and a backup/secondary boiler (~$306,000) to improve energy efficiency and reliability. Mr. Fabrizio asked that the committee recommend bringing two CM3 contracts (one ~ $306,000, one ~ $89,000) to the board for approval and noted the items are available on COSTARS.

Why it matters: repairs affect building systems that enable cooling and heating; using escrowed funds for energy‑saving replacements could reduce future operating costs but requires board approval and, in the glycol case, insurance resolution.

What’s next: staff will ask for board approval of the CM3 contracts for the pumps and boiler in April and continue working with the insurance broker on the glycol‑pipe repair claim.