Council approves SEED loan and task order amendment for 9th & Lincoln lift station project

Sunnyside City Council · March 24, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Sunnyside accepted a Yakima County SEED loan award of $569,720 (10‑year repayment at 5.06%) for the 9th & Lincoln lift station replacement and authorized the interim city manager to sign contract C 2026‑2; council also approved a task order amendment with HLA to add construction engineering and administration, with bids opening April 1 and construction anticipated to start June 1 (typical 90‑day timeline).

The Sunnyside City Council on March 23 approved two related measures to move forward on the 9th & Lincoln lift station replacement.

Hector, a city project staffer, told council the Yakima County Development Association's SEED board and county commissioners approved funding for the project in the form of a loan anticipated at $569,720, repayable over 10 years at a 5.06% interest rate (the county's interfund rate). Council voted to authorize the interim city manager to sign the resulting contract (C 2026‑2) so the city can enter into the loan agreement.

Council also approved an amendment to task order 2024‑11 with HLA Engineering and Land Surveying to provide construction engineering and administration services for the project; staff said those costs were included in the SEED funding award. Staff reported bids will open April 1 in the City Hall basement, and that construction is anticipated to begin June 1, subject to long‑lead items (pumps and control panels). A staff engineer estimated a typical construction timeline of roughly 90 days, with some on‑site work before long‑lead equipment arrives.

Council approved both measures on roll call.

The resolutions authorize the interim city manager to finalize contract and taskorder signings and direct staff to proceed with the procurement and construction schedule described.