Public works superintendent briefs committee on River Road, Serny Park and 2025 road program
Summary
Superintendent Jamie Clark updated the committee on recent capital maintenance projects: River Road curb and gutter is complete and mostly county‑funded, Serny Park Phase 1 is largely finished with punch‑list items remaining, and the Sanchez Drive 2025 road program is nearing paving and expected to finish under budget.
Superintendent Jamie Clark briefed the committee Oct. 13 on capital maintenance and replacement plan projects including River Road, Serny Park Phase 1 and the 2025 road program.
Clark said River Road work included installation of approximately 1,500 feet of 12‑inch storm sewer, 30 catch basins, about 4,000 feet of contractor‑installed curb, and contractor landscaping. He said the project…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat