Water staff warn of aging pipes, recent $900,000 emergency repair and a $200,000 tank fix
Summary
Hurricane City water staff described recurring breaks in older galvanized/chlorinated pipe, a recent emergency repair costing about $900,000, a recommended $200,000 roof/epoxy repair for the West tank to avoid a multi-million-dollar replacement, and proposed a water-facilities manager role.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City water staff told council members that sections of older pipe installed years ago are deteriorating and causing repeated breaks, and that recent emergency work cost roughly $900,000. "We spent about $900,000," the water presenter said, describing a recent emergency repair and subsequent installation of a 14‑inch ductile line.
The presenter highlighted a specific vulnerability in the city's West tank, saying water has puddled on the roof and caused cracking where tension wires pass across the surface. Staff reported they found a contractor who proposed a self-leveling adhesive and epoxy coating to stop ponding and cracking, and provided a low repair estimate of approximately $200,000 to protect the tank's roof. The presenter warned that without repair the city could face a full tank replacement on the order of $3,000,000.
Rates and funding: staff said the cost of material and repairs in affected subdivisions will likely require a return to the council for rate adjustments. "So we're probably gonna have to come back with some rate increases in order to be able to pay for workings with this," a staff member said.
Operations and staffing: water staff proposed creating a dedicated water facility manager position to centralize inventory, maintenance and MS4 compliance across pumps, PRVs and other facilities. The proposal argued that a full-time position would keep facilities inspected, manage inventory (which historically has not been audited) and improve maintenance scheduling.
Next steps: staff will refine cost estimates and bring formal budget requests forward; council members asked for follow-up on funding sources and timing, with some discussion about continuing to use outside consultants while building in-house capacity.