Engineer reports Sandy Street project 54% complete; water treatment plan about 60% finished amid likely new water-hardness rule
Summary
An engineering consultant reported progress on Sandy Street project, sandblasting and easement work, completion of a hydraulic model, and that the water treatment plan is roughly 60% complete; staff said an expected state rule on water hardness is being folded into the design and will require more equipment and chemicals.
An engineering update presented to the Harswell Trousers Sewer Utility Board reported progress on multiple system projects and noted a forthcoming state-level requirement that may force design changes.
The chair introduced an engineering report for Mr. Evan White of Mid 10 Engineering. White said the Sandy Street Road project was "about 54%" complete and that tank sandblasting with a preferred vendor is scheduled and expected to finish…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat