City extends Oakdale Alameda project timeline, approves $113,916 contract amendment
Summary
City Engineer Mario Sanchez told the council the Oakdale Alameda Street Beautification Project is about 65% complete and that design changes extended the completion date to March 2025; the council approved a $113,916.38 amendment to the construction management contract with Unico Engineering.
Get email alerts on the Construction Management topic
No spam. Unsubscribe anytime.
The El Cajon City Council approved a $113,916.38 amendment to the construction management contract with Unico Engineering for the Oakdale Alameda Street Beautification Project after staff reported design changes during construction extended the project completion date from December to March 2025.
Mario Sanchez, city engineer, said the project is approximately 65% complete and that design changes — including reinstating some parking to accommodate businesses, repaving Walter Way and completing alley and sidewalk work — required additional construction management effort. Sanchez said the project is funded with ARPA, a Clean California grant and TransNet funds. Council members asked about the reasons for modifications and whether residents were being kept informed; staff said one complaint was received about limited parking during construction and that the resident was kept informed.
A motion to approve the contract amendment carried unanimously. No public speakers were present on the item.