District hears E-rate plan to replace firewall, UPS and switches; project estimated at about $271,705
Summary
Wayne County RESA technology coordinator Jonathan Turner presented the South Redford School District's FY26–27 E-rate upgrade: timeline (June–Oct 2026), vendor recommendations and a total project estimate of $271,705, with the district portion reported as roughly $90,000. Board members asked about firewall layers, funding sources and USAC timing.
Get email alerts on the Technology topic
No spam. Unsubscribe anytime.
Jonathan Turner, technology coordinator with Wayne County RESA, told the South Redford Board of Education on March 9 that the district is seeking federal E-rate discounts to replace aging uninterruptible power supplies, upgrade switches and replace the district firewall as part of a FY 2026–27 technology project.
Turner described the district network topology and E-rate funding categories and said the district sent an RFP in February and received six bids. He recommended line-item awards for fiber maintenance (lowest bidder AMCOM, about $56,000), UPS units (Vector Technology), a firewall replacement (Delta Network Services, about $70,000), switches (Intercom, $23,360) and smart-net support (Inicop, $8,045). "The entire project is gonna cost about $271,000. $271,705," Turner said, adding the district's out-of-pocket responsibility would be taken from the technology budget allocation and E-rate program.
The presentation included a projected timeline: work to begin approximately June 2026, run into October 2026 and require USAC approval of the E-rate reimbursement (Turner said reimbursement is anticipated roughly 16 weeks after project completion). Turner said the district's current UPS units are five to seven years old and, following a recent outage, need replacement to restore phone and network resiliency.
Board members questioned network security and funding. One member asked whether a single firewall could be bypassed given the number of buildings; Turner said all district traffic routes to the main firewall in the data center and offered to follow up with his network team about firewall layers. On who pays if E-rate were discontinued in the future, Turner said: "Once we do start the work, they can't take it away from us; in the future, if they do so choose to get rid of the E-rate program, then, yes, it would be a district purchase." The board clarified that non–E-rate components would be paid from the tech bond budget and the district's share from the technology budget.
Next steps: the cabinet and RESA team evaluated the bids and recommended awardees; the district will proceed with contract documentation and pursue USAC approvals before implementation. The board requested a copy of Turner's presentation and asked staff to return with any follow-up details on the firewall architecture and exact district cost share.