City presentation: Highway Safety Improvement project update; Imperial Construction reported as low bidder

Manassas Park governing body · March 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Calvin O'Dell, Manassas Park director of community development, presented an update on the city's first Highway Safety Improvement Program project, recapping a VDOT funding agreement, a local obligation of $58,292, design costs of about $161,000, and reporting Imperial Construction LLC as the low bidder from November 2025 bids.

Calvin O'Dell, director of community development for the City of Manassas Park, briefed the governing body March 17 on the city's first project under the Highway Safety Improvement Program and the procurement timeline and costs.

O'Dell said the city previously authorized an application for FY24 Highway Safety Improvement funds and entered a funding agreement with the Virginia Department of Transportation (VDOT) on May 4, 2023. He said the agreement included $1,220,000 in total funds for the project, that the city is obligated for $58,292 in local funds, and that roughly $161,000 had been spent on design. O'Dell noted the city advertised the project in October 2025, received bids in November 2025, and that Imperial Construction LLC submitted the low bid when bids were opened on Nov. 13, 2025.

O'Dell provided cost components including construction engineering and inspection, VDOT oversight, and contingency in the packet; he said Imperial was the low bidder and summarized that the remaining construction estimate was reported in the presentation materials. Council did not take a vote on the presentation; it was provided as an informational update and to document the procurement history.

Next steps for the project include finalizing contracts and coordinating with VDOT on construction oversight and contingencies; staff indicated further reporting and contract documents would follow in subsequent meetings or administrative actions.