Stockton approves underground utility district for Lower Sacramento Road using PG&E Rule 20A funds

Stockton City Council · August 20, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council adopted a resolution to form an underground utility district on Lower Sacramento Road to allow PG&E to use Rule 20A funds for undergrounding overhead utilities; project cost was estimated at about $4.1 million and completion anticipated in 2028-29.

The Stockton City Council on Aug. 20 approved a resolution to establish an underground utility district on Lower Sacramento Road between Pixley Slough and Bear Creek, clearing the way for PG&E to use Rule 20A funds to underground overhead utilities.

Public Works staff told the council the Rule 20A program (established by the California Public Utilities Commission) requires a formal underground-utility-district designation before PG&E can expend allocated funds. Staff said Stockton's current allocation for Rule 20A is roughly $4.8 million; the Lower Sacramento Road project was estimated at roughly $4.1 million. The project length was presented as approximately 1.6 miles (roughly 4,100 linear feet), and staff estimated project completion in 2028 or 2029, depending on PG&E priorities and scheduling.

Director of Public Works (speaker 55) recommended adoption of the resolution, approval of a CEQA notice of exemption, and authorization for the city clerk to notify affected utilities and property owners. After a brief public hearing and no substantive public opposition, council approved formation of the district by roll-call vote (motion passed 6-0; Vice Mayor Walmsley absent). The council noted that PG&E will serve as lead agency and that project timing depends on PG&E's internal schedule.

The council's action allows the city to pursue use of Rule 20A funds set aside on Stockton's behalf and to move forward with stakeholder notification and required environmental-clearance formalities.