Consultant: Terra Vista drainage and road fixes underway but wet weather could delay pond work
Summary
Consultants and staff told the Williamson County Planning Commission there remain 27 open items on the Terra Vista drainage and erosion-control bond, with access-road work expected first and pond stabilization hoped for by early summer, but officials cautioned April–May weather may delay work.
Brent Thany, a consultant with Truland Consulting representing Jones Company, told the Williamson County Planning Commission that contractors walked Phase 1 last week and a geotechnical engineer has submitted a draft follow-up letter addressing retaining-wall comments.
Thany said Detention Pond 5 remains too wet to enter and that crews are tentatively scheduled to attempt repairs as soon as the ground dries. He summarized…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat