Board votes to award $830,067 Farmington Elementary roof contract to ARC Roofing

Germantown Board of Education · March 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Germantown Board of Education unanimously approved bid GMSD FY26 001 to replace and restore the Farmington Elementary roof, awarding the $830,067 contract to ARC Roofing; the project will be paid with capital improvement funds from the Shelby County Commission and may incur future change orders for wet insulation.

The Germantown Board of Education voted unanimously to approve bid GMSD FY26 001, awarding a contract to ARC Roofing Incorporated for $830,067 to repair, restore and replace the roof at Farmington Elementary School.

Superintendent Mr. Manuel told the board the roof, estimated at 15–20 years old, has deteriorated to the point that repeated leaks require replacement rather than continued patching. He said the district received four bids and recommended ARC Roofing as the low bidder with prior work at Riverdale cited as relevant experience.

Vice Chair Griffith moved the motion to approve the bid, which was seconded by Mr. Hendricks and Mr. Ellis. During discussion board members pressed for clarity about potential wet insulation under the roof deck; Mr. Manuel and staff said bidders provided a per‑square‑foot price for wet insulation but the final cost will not be known until the existing roofing is removed and the contractor documents the amount needing replacement. The superintendent said necessary replacement insulation would appear as a change order and that his authority to approve change orders is limited by dollar thresholds, with larger change orders returning to the board.

The motion, recorded as agenda item 9A, passed on a roll‑call vote: Mr. Strain — yes; Mr. Hendricks — yes; Ms. Griffith — yes; Mr. Ellis — yes; Chair Curry — yes. The board noted the new roof is expected to have a minimum useful life of 20 years and possibly up to 30 years.

Funding for the project will come from capital improvement funds provided by the Shelby County Commission; the board and administration said this project had been on the district’s five‑year facilities list.

Next steps: staff will finalize the contract paperwork, schedule demolition and replacement work, and present any change orders over the superintendent’s authorized threshold to the board for approval.