Pflugerville bond advisory panel reviews proposed FM 685 relief routes, Melber Lane and downtown parking
Loading...
Summary
At a bond advisory meeting, city staff presented a package of FM 685 "relief routes," three major roadway projects and a downtown parking proposal totaling roughly $104 million for the transportation/downtown slate (preliminary estimates raise the broader program near $185 million); committee members asked for more fiscal context and scheduled financial review on April 20.
City staff and the Capital Improvement Bond Committee spent the meeting revisiting the committee’s vision and mission and reviewing candidate projects proposed for a potential 2026 bond package, focusing on a package of FM 685 “relief routes,” Melber Lane, Kelly Lane phase 3 and a downtown public-parking project.
Angela Point, senior project manager with WSB, told the committee that the three transportation projects plus one downtown project shown that night amount to “about a $104,000,000,” and that when combined with prior items the rough program total is “about $185,000,000,” subject to refinement. Staff emphasized that many design elements are already funded and that the bond request would primarily cover construction and right-of-way for several items.
Why it matters: committee members repeatedly pressed staff for clearer financial context — how much remains unspent from prior bonds, what parts of each project are already funded by developers or other sources, and what the tax impacts could be if the city issues general-obligation debt. Staff said the April 20 meeting will bring bond counsel, the finance director and scenarios showing tax implications so committee members can better assess community impacts.
What staff presented: the relief-route package was described as a proactive set of alternate north–south and east–west connections intended to reduce congestion on FM 685 and to ease traffic during any future widening work on the state-owned 685 corridor. Staff provided segment-level sketches and preliminary cost estimates:
- Old Austin Hutto Road extension: a three-lane link with shared-use paths, estimated at about $17.1 million; design is funded and some land acquisition would be included in the bond request.
- Fenning Lane north extension: a north–south connection serving the Amazon-area stub and a future east–west tie, estimated at roughly $14.3 million; currently in design.
- Fenning Lane south extension (south of Pecan): to connect to Wells Branch Parkway with a three-lane configuration and shared-use paths, estimated at about $14.5 million and in design.
- Terrell Lane extension and floodplain crossing: still under study with three alignment options; staff said the most expensive option was estimated at about $20.6 million to address drainage and environmental constraints.
Staff said the relief-route package (land, permitting, utilities, construction) was being budgeted at approximately $66.5 million overall, and that consultants have modeled before-and-after traffic scenarios to estimate how much congestion would be relieved on FM 685.
Other transportation projects and partnerships: staff outlined Melber Lane, a new four-lane divided roadway on the city’s east side, with construction funding requested at about $18.1 million and a developer contribution of $5.5 million already committed. Kelly Lane phase 3 — the final phase to convert the rural two-lane road to a four-lane divided section with roundabouts and shared-use paths — was listed at about $14.3 million. Staff noted many projects will include drainage work but not necessarily utilities, depending on the segment.
Downtown parking: staff proposed a $5.15 million package to finance a parking analysis, secure land for short-term surface parking and build surface lots as an interim strategy while preserving options for a future parking structure if demand materializes. Staff framed parking as a catalyst for downtown revitalization and said a later feasibility/design phase for a structure would be an additional cost beyond the $5.15 million allocation.
Committee questions and requests: members asked for clearer cost breakdowns (what the bond would cover versus existing funding sources), estimates of additional ongoing operations and maintenance costs (police, fire, EMS), more explicit traffic-model results showing the percentage congestion reduction on FM 685, and a table that lists for each project what is funded already (design, ROW, developer contributions) and what the bond would pay for. Staff agreed to produce a project table, circulate links to prior studies, and prepare tax-impact scenarios with bond counsel and the finance office at the next meeting.
Scoring and next steps: the committee used a live Mentimeter evaluation to score projects on strategic alignment, feasibility/confidence, community benefit and equity/safety. Preliminary scores showed stronger feasibility and perceived benefit for Kelly Lane and the relief-route package and lower feasibility ratings on the downtown parking item in the initial scoring. Staff will compile committee scores into recommended scenarios for the April 20 meeting; the committee expects to finalize a recommendation on May 18 for presentation to the city council later in May.
No formal project approvals were made at this meeting; the only formal action recorded in the minutes was approval of the March meeting minutes by voice vote. Staff emphasized the numbers are preliminary and will be refined with bond counsel and financial staff before any formal bond proposal is presented to council.
Next meeting: staff scheduled an April 20 session to present bond-package financial scenarios with bond counsel and the finance director; May 18 is the anticipated date to finalize the committee’s recommendation for council consideration.

