Forest Lake council presses consultants to trim $48.8M public works facility proposal

Forest Lake City Council (workshop) · April 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultants presented a schematic design for a consolidated Public Works facility (about 119,000 sq ft) with a schematic estimate near $48.8 million; council favored options that reduce cold-storage footprint and material costs and asked staff to pursue a $35M—$40M target and bring alternates back for bid-day decisions.

Consultants from Wold and KA presented schematic designs and cost estimates for a consolidated Forest Lake Public Works facility, and council members pressed for cost reductions and clearer budget targets.

Jonathan (Wold) summarized the program and site constraints and reported the schematic estimate: "So, again, currently, we're at about that 48,800,000.0," he said, describing a project that grows to roughly 119,000 square feet in the full 20-year build-out concept. KA's facility condition assessment documented roughly $4.6 million in deferred maintenance across six existing public-works facilities and recommended consolidation in part because some buildings are in critical condition.

The design includes office space, division workshops, multiple mechanics bays, a wash bay, a mezzanine for building systems and a cold-storage building for seasonal equipment. Consultants told the council that cold storage sized at roughly 16,000 square feet accounted for about $4 million of the schematic price; resizing to about 10,000 square feet could cut roughly $900,000 from the total. The core planning group's recommendation was option 3b: retain cold storage as a pre-engineered metal building (PEMB) while reducing maintenance space.

Council members and staff discussed trade-offs: maintaining future expandability, meeting operational needs (lube rooms, parts storage, shops), waiving internal permit/utility fees for the city project and using alternates at bid day to preserve options. Several members favored carrying cold storage as a bid alternate so the city can decide at bid day whether to build the larger facility. Jonathan and KA emphasized that many material and soft-cost choices will be refined in design development and that bringing a construction manager on early can reduce contingency and improve bid competitiveness.

On delivery methods, consultants explained options and trade-offs: low-bid general contracting, construction-manager-as-agent (CMA), and construction-manager-at-risk (CMAR). They noted CMAR/CMA add transparency and prequalification controls but can increase bonding and insurance costs (roughly a 1% bond and 1% insurance factor on large projects) and add consultant/management fees.

Council direction: members indicated a preference for keeping the schematic layout's operational components while pursuing options to reduce cost toward a $35M—$40M target and asked staff and the steering group to refine alternates, value-management options and schedule before returning with a recommended path into design development.