Board approves ARPA‑funded design and change‑order increases for school auditorium and stadium projects
Summary
The board approved multiple ARPA‑funded amendments — including a $495,243 auditorium change order and design/allowance increases for school lighting and soffit design — with staff saying the timing allowed work to proceed while seats and systems were out of service.
The Danbury City Board of Awards on Dec. 11 approved a series of American Rescue Plan Act‑funded contract amendments for school and public‑assembly projects, including a large change order to finish auditorium work and smaller allowances to cover possible unforeseen conditions on lighting projects.
Purchasing agent Jake Volkin said the Denver Heights auditorium project, previously awarded to J. Rosen Construction for $1,088,409, needs a $495,243.02 change order to cover replacement of the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat