Board hears TES HVAC replacement timeline and approves middle- and high-school service contracts
Summary
At its March 9 meeting the Tyronox USD 4 6 board received a detailed schedule for elementary HVAC replacement from Mr. Loomis and approved service agreements for the middle and high schools — Helm for TMS (not to exceed $10,272) and a THS contract (not to exceed $92,580).
The Tyronox USD 4 6 Board of Education on March 9 received a detailed presentation on the elementary (TES) HVAC replacement schedule and voted to approve two HVAC service agreements for the middle and high schools.
Mr. Loomis, who the chair introduced to give the presentation, said Universal Construction supplied a month-by-month draw schedule showing how bond contingency funds and capital balances will be spent across the 2025–26 and 2026–27 fiscal years. “This kind of breaks down our financial implication by month,” he said, describing the schedule as a planning tool rather than a change to the project scope.
He told the board the summer construction plan divides TES into six classroom “pods.” The first pod is scheduled for completion on July 6, with…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat